Plumbing wall 2nd floor

So far we have plumbing for the basement unit completed. Our goal now is to finish the remaining plumbing for the 1st and 2nd floor, even though we won’t start in earnest on the 2nd floor until next year.

That means that Drew and I have to continue with our plumbing wall installation on the 2nd floor, pretty much in the same way as we did for the 1st floor.

The plumbing wall sections facing the kitchen and bathroom lined up beautifully with those on the 1st floor, leaving us with a five inch gap in between for the utilities. It is nice to have the pieces of a puzzle fall into place.

Like on the 1st floor, we left an opening for a medicine cabinet in the bathroom wall section, in case we decide to install one later.

About Marcus de la fleur

Marcus is a Registered Landscape Architect with a horticultural degree from the School of Horticulture at the Royal Botanic Gardens, Kew, and a Masters in Landscape Architecture from the University of Sheffield, UK. He developed a landscape based sustainable pilot project at 168 Elm Ave. in 2002, and has expanded his skill set to building science. Starting in 2009, Marcus applied the newly acquired expertise to the deep energy retrofit of his 100+ year old home in Chicago.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.