This is one of those tasks that I have to complete before we can continue with the insulation installation.
You may recall that we had the closed cell foam recently installed. Next up is the open cell installation.
The open cell foam will be sprayed on top of the closed cell foam that’s already in place, up to the back of the studs. The little gap between the studs and the oak trim is our problem. To be able to spray the foam we need to have a surface to spray against. With the gap as it is now, the foam would get all over the place, making a mess.
We needed to close that gap. We had the additional trim at hand already, thanks to The ReBuilding Exchange. Cathy had already cleaned the trim so my next step was to figure out how to make it fit.
Because most of the pieces were not long enough, I needed to join them. I squared the short ends that I was about to join and got my dowel kit out, including the right sized drill and dowel center pins to align the dowel holes.
Once the pieces were joined together, I needed to cut them to the right length and depth. Not an easy task in an old building where hardly anything is square.
Cutting the length was actually relatively easy. But cutting it to the right depth…
My solution was to mount a strip of 5/8 inch drywall to the adjacent stud. This allowed me to hold the trim piece in place and mark where the drywall meets the trim.
I had to repeat the procedure for the other side and the trim header too. This way I was sure to cut the trim to the right depth.
The original trim was joined into one piece: The trim header was attached to the top of the sides. I took this as a clue and decided to join the trim extension the same way. To put the three pieces together, I laid them out on the floor, squared them and joined them with finishing screws.
To get a good and even connection between the original trim and the extension, I again used wood dowels.
I now could lift the extension into place. I pushed them tightly onto the wood dowels, making sure everything was straight and square, and attached the new trim to the adjacent framing with finishing screws.
The gap is plugged and another item struck of the to-do list. The next line in the list says: Plumbing. Hmm.






I do really like your concept of using dowels – reminds me of my father building costum furniture back home. Dowels make sure for a stable but hidden connection. With the dowel center pins you just have to make sure to drill straight otherwise the dowels will not fit properly – I can tell by own experience…